Implementation method

A 28-week implementation, run by the client's team.

Pramaan uses an SAP Activate-aligned sequence: fit-to-standard first, configuration in sprints, and gates that stop the programme from drifting. The scope for the first release is finance and HR: FI, CO, personnel administration, organisational management, time and payroll.

The six gates

Swipe to see all columns →

PhaseWeeksOutcomeGate
0 · Mobilise1–2Team, scope, tenant, data profile, decision logSigned charter and plan
1 · Discover3–5Fit-to-standard, process baseline, target designValidated scope baseline
2 · Explore6–11Blueprint for FI, CO, HR, time and payrollSigned blueprint
3 · Realize12–21Configuration, extensions, integrations, dataSIT exit
4 · Deploy22–25UAT, cutover, parallel payrollUAT sign-off
5 · Run26–28Hypercare, handover, benefits baselineService acceptance

Release 1 scope

One scope baseline after Explore. New scope enters through the change board, not a corridor conversation.

FI

General ledger, AP, AR, asset accounting, tax, bank integration

CO

Cost centres, internal orders, WBS, allocations, margin analysis

PA

Personnel administration: employee master, actions, org assignment

OM

Organisational management: units, jobs, positions, reporting line

Time

Work schedules, attendance, absences, overtime, payroll input

Payroll

Indian payroll, statutory deductions, parallel run, postings

Data before cutover

Master data is profiled in week 3, not in the cutover window. Every object has a source, owner and validation rule.

Parallel payroll

At least one full parallel payroll before go-live. The payroll register must tie to the FI/CO postings.

Evidence of readiness

SIT, UAT, cutover rehearsal and a signed service acceptance. No gate is waived for speed.