Overall readiness
70%
Pramaan · ERP audit
SAP PM pack · v1Twenty checks across thirteen SAP PM domains — the first Pramaan ERP audit pack. Every score opens to the records behind it, the benchmark it breached and the transaction that fixes it. Finance and HR packs follow.
System / client
SAP S/4HANA · 100
Plant
1000 · Combined Cycle Power Plant
Audit date
2026-11-14
Lead
Demo assessment
Framework
v1.0.0 · 20 of 50 checks
Overall readiness
70%
Audit opinion
Amber
Open findings
6
Risk index
30
Check coverage
20/50
Sorted by the weakest domain. Colour follows the audit opinion, not the percentage alone.
Audit opinion
Amber
Material gaps exist but none is beyond recovery. Fix the critical records first; the percentage follows.
Findings by severity
A domain can be highly compliant and still carry a critical gap. The opinion counts critical failures separately; a high percentage never clears them.
Master data and transactional health, by audit domain.
13 domains · 20 checks
Swipe to see all columns →
| Domain | Section | Checks | Pass | Fail | Readiness | Opinion | |
|---|---|---|---|---|---|---|---|
| Functional locations | Master data | 2 | 1 | 1 | 50% | Red | |
| Equipment master | Master data | 2 | 1 | 1 | 50% | Red | |
| Equipment & FL BOMs | Master data | 1 | 0 | 1 | 0% | Red | |
| Work centres & capacity | Master data | 1 | 1 | 0 | 100% | Green | |
| Task lists | Master data | 2 | 2 | 0 | 100% | Green | |
| Measuring points | Master data | 2 | 2 | 0 | 100% | Green | |
| Maintenance plans | Master data | 2 | 2 | 0 | 100% | Green | |
| Catalogs & codes | Master data | 1 | 0 | 1 | 0% | Red | |
| Notifications | Transactional | 2 | 1 | 1 | 50% | Red | |
| Orders & backlog | Transactional | 2 | 1 | 1 | 50% | Red | |
| Scheduling & dates | Transactional | 1 | 1 | 0 | 100% | Green | |
| Confirmations | Transactional | 1 | 1 | 0 | 100% | Green | |
| Reservations | Transactional | 1 | 1 | 0 | 100% | Green |
Swipe to see all columns →
| Check | Domain | Severity | Result | Exceptions | Benchmark | |
|---|---|---|---|---|---|---|
| FL-02Active FLOCs missing plant or cost centre | Functional locations | Critical | Fail | 28/22013% | 0% of active FLOCs missing plant or cost centre | |
| FL-03Active FLOCs without ABC criticality | Functional locations | High | Pass | 5/2202.3% | < 5% of active FLOCs without ABC criticality | |
| EQ-02Class A equipment missing OEM or model | Equipment master | High | Pass | 2/2460.8% | < 2% of Class A equipment missing OEM or model | |
| EQ-03Equipment not installed at a functional location | Equipment master | Critical | Fail | 55/8346.6% | < 5% of active equipment not installed at a FLOC | |
| BM-01Class A equipment without a spare-parts BOM | Equipment & FL BOMs | High | Fail | 48/24620% | >= 90% of Class A equipment has a BOM | |
| WC-02Work centre without capacity | Work centres & capacity | Critical | Pass | 0/240% | 100% of PM work centres have a capacity header | |
| TL-01Task lists not released | Task lists | High | Pass | 7/1504.7% | >= 95% of task lists released | |
| TL-02Operations with zero planned work | Task lists | Critical | Pass | 0/10810% | 0 operations with zero planned work | |
| MP-01Running-hour points not flagged as counters | Measuring points | High | Pass | 0/900% | 100% of counter points flagged as counters | |
| MP-02Condition points without warning limits | Measuring points | High | Pass | 5/905.6% | >= 90% of condition points have limits | |
| PL-01Plans never scheduled | Maintenance plans | Critical | Pass | 0/1600% | 0 active plans left unscheduled | |
| PL-03Plan items without a task list | Maintenance plans | Critical | Pass | 0/3160% | >= 95% of plan items have a task list | |
| CT-02Generic codes dominate the catalogs | Catalogs & codes | High | Fail | 93/42022% | < 15% generic codes in active catalogs | |
| QM-01Open notifications older than 60 days | Notifications | High | Fail | 35/12129% | < 10% open notifications older than 60 days | |
| QM-03Closed breakdowns without failure codes | Notifications | Critical | Pass | 7/2063.4% | >= 95% of closed M2 notifications carry failure codes | |
| AU-01CRTD orders older than 30 days | Orders & backlog | High | Pass | 3/803.8% | < 5% CRTD orders older than 30 days | |
| AU-02Confirmed orders stuck before TECO | Orders & backlog | High | Fail | 40/11036% | 0 CNF orders older than 30 days | |
| AF-01Released orders past their finish date | Scheduling & dates | High | Pass | 17/1889.0% | < 15% released orders past basic finish | |
| FR-04Completed orders with zero confirmed hours | Confirmations | High | Pass | 40/10723.7% | < 5% completed orders with zero confirmed hours | |
| RS-01Open reservations on completed orders | Reservations | High | Pass | 0/10720% | 0 open reservations on TECO/CLSD orders |
Method
Readiness
Passed checks divided by evaluated checks. N/A checks are excluded from both sides.
Risk index
Severity-weighted failures: Critical 5, High 3, Medium 1. Zero is a clean system; 100 is every evaluated check failed.
Audit opinion
Green at 85% readiness with no critical gaps. Amber at 70% with at most two. Everything else is Red.
Swipe to see all columns →
| Check | Title | Domain | Severity | Benchmark |
|---|---|---|---|---|
| FL-01 | Structure indicator not standardised | Functional locations | High | 100% standard hierarchy (KKS or ISO 14224) |
| FL-04 | Orphan functional locations | Functional locations | Medium | 0 orphan sub-locations outside the plant tree |
| EQ-01 | Equipment without object type | Equipment master | High | < 2% equipment without a standard object type |
| EQ-04 | Duplicate or scrapped assets still active | Equipment master | High | 0 duplicate active equipment records |
| EQ-05 | Missing start-up date or asset link | Equipment master | Medium | > 95% major equipment linked to a fixed asset |
| BM-02 | BOM items with blocked or obsolete materials | Equipment & FL BOMs | High | 0 obsolete materials in active PM BOMs |
| BM-03 | FL BOMs not using usage 4 (PM) | Equipment & FL BOMs | Medium | 100% PM BOMs created under usage 4 |
| WC-01 | Work centre maintenance indicator or deletion flag | Work centres & capacity | High | All craft disciplines represented and active |
| WC-03 | Work centre missing cost centre or activity type | Work centres & capacity | Critical | 100% linked to active CO activity types |
| TL-03 | Generic one-line task list operations | Task lists | Medium | > 85% operations have actionable steps |
| TL-04 | Task lists missing material components | Task lists | High | > 80% major lists include required spares |
| MP-03 | Counter rollovers or negative deltas | Measuring points | Medium | 0 unvalidated rollovers in 12 months |
| PL-02 | Call horizon not set for long-lead work | Maintenance plans | High | 80–90% call horizon for overhaul plans |
| PL-04 | Overdue maintenance calls | Maintenance plans | Critical | 0 calls stuck in save-to-call beyond 14 days |
| PL-05 | Single-counter plans on critical rotating assets | Maintenance plans | Medium | Multi-counter strategy on turbines and compressors |
| CT-01 | Failure catalogs incomplete or inactive | Catalogs & codes | High | All B/C/5 catalogs active and structured |
| CT-03 | Catalog profiles not assigned to notification types | Catalogs & codes | High | 100% of M2 types enforce a catalog profile |
| QM-02 | Breakdown notifications missing downtime start | Notifications | High | 0 M2 notifications without a malfunction start |
| QM-04 | Corrective orders created without a notification | Notifications | Medium | > 90% corrective orders linked to a notification |
| AU-03 | TECO orders not business-closed after 90 days | Orders & backlog | High | Monthly settlement and CLSD closure |
| AU-04 | Orders without a technical object | Orders & backlog | Critical | 0 maintenance orders without equipment or FLOC |
| AU-05 | Released orders without a settlement rule | Orders & backlog | Critical | 100% released orders have a settlement rule |
| AF-02 | Reactive vs preventive order mix | Scheduling & dates | High | 70–80% planned work; < 20% breakdown |
| AF-03 | Preventive orders generated without a task list | Scheduling & dates | High | 100% preventive orders inherit a task list |
| AF-04 | Operations missing a work centre | Scheduling & dates | Critical | 0 operations without a craft work centre |
| FR-01 | Actual hours identical to planned on every order | Confirmations | Medium | < 30% 1:1 confirmations |
| FR-02 | Confirmation lag beyond 48 hours | Confirmations | Medium | Confirmations entered within 24–48 hours |
| FR-03 | Partial confirmations left open | Confirmations | High | Final confirmation set on completion |
| RS-02 | Past-due reservations with no withdrawal | Reservations | Medium | Monthly cleanup of stale reservations |
| RS-03 | Non-stock items without a purchase requisition | Reservations | High | 100% non-stock items generate a PR |
The words that decide which rows enter a check.
What is real here
The rule engine, the scoring and the evidence drill are real. The rows are a deterministic demonstration dataset for a combined-cycle plant. This is the SAP PM pack of the Pramaan ERP audit; finance and HR packs are next. No SAP system is called, and this is not an SAP-certified audit.
The next step is an import of SE16N extracts; the same engine runs on those tables without a server round trip.